SUBJECT PROPOSED ERECTION AND COMPLETION OF A 300 CAPACITY GIRLS DORMITORY WP ITEM D31, CE/TKAW 801 JOB NO. 8340A





Further to your request through your letter dated 9th September, 2009 we herewith forward a copy of the bills of quantities of the dormitory whose drawing you have already approved.
Please note that the estimated cost of the dormitory is Kshs 38,140,921.80 broken as below
Builders work - Ksh 20,876,105.00
Prime cost and sums
Electrical works - Ksh 2,100,000.00
Plumbing and drainage - Kshs. 3,000,000.00
Civil Works - Kshs. 2,500,000.00
Contingencies - Kshs. 2,500,000.00
NB: Civil works comprise Septic Tank, foul drainage and storm water drainage.
Particular preliminaries - Kshs. 1,700,000.00
The particular preliminaries comprise project management expenses and Clerk of Works expenses over a period of one year the project is expected to take to complete.
VAT - Kshs. 5,260,816.801
Please note that the preliminary estimate passed to you earlier did not include the VAT component.
Your approval of the Bills of Quantity and the Project Budget is required. We should thereafter issue you additional copies of the BQ and draft advertisement to tender for the works. We herewith forward a tentative programme of these works.
As discussed with our Mr. Osoro, the Laboratories were to be replanned to be two storey to save land. We will forward the drawings and estimates shortly.
Arch. P. S. Wasike
Senior Principal Supt. Architect
For: PERMANENT SECRETARY
DORMITORY FOR ST. FRANCIS GIRLS HIGH SCHOOL-
WP ITEM NO. D31 CE/TKAW 801 JOB NO. 8340A
PROPOSED PROGRAMME FOR THE WORKS
ITEM |
EVENT |
TIME PERIOD |
KEY DATES |
ACTION BY |
Advertise for the Works in Local Dailies |
3 weeks (Have on papers on 2/11/09) |
2nd Nov 2009 to |
School Board |
|
Open Tenders (at the school) |
½ day |
24th Nov. 2009 |
School board & project Manager (Chief Architect0 |
|
Issue received tender to Project Manager for analysis |
½ day |
24th Nov. 2009 |
School Board |
|
Analyse Tenders and sub mit Report to School Board |
2 weeks |
25th Nov 2009 |
Project Manager |
|
Adjudicate and award Tender |
1 week |
14th to 18th Dec, 2009 |
School Board |
|
Appeals Period |
2 weeks |
18th Dec 2009 |
Tenderers |
|
Mobilization |
2weeks |
4th Jan 2010 |
Tenders |
|
Construction |
52weeks |
18th Jan, 2010 |
Contractor |
|
|
|
|
|
REPORTING OFFICIALS AND EVALUATION
- BOARD OF GOVERNORS
- SCHOOL INFRASTRUCTURE COMMITTEE(SIC)
- MOPW- PROJECT MANAGER
- DIC\STRICT EDUCATION BOARD
- PTA
PROJECT SUATAINABILITY
Besides the parent’s Mandatory contributions as passed by Min 7/07/11/09 PTA (AGM), all the stake holders need to be involved.
The B.O.G. needs an aggressive programme for sourcing and management of Resources for this project.
Any form of assistance- Financial, Material, Technical would be immortalized in the Generations of Girls who would be educated at our school.